On Monday, 20 February, at 10 am traffic regulations will change on Pronksi street. On Pronksi and Jõe streets one lane will be opened on both streets in both directions.
Today, on 21 February, the new building of Tallinn Rõõmupesa kindergarten (A. H. Tammsaare tee 141) was officially opened in Mustamäe district. The building, which has ten classrooms, can accommodate up to 240 children. The nursery has recreation classes, a gym, a hall and a study room.
From 7 March, construction works will start for the first phase of the Vanasadama tramline, causing changes in the traffic regulation in the city center. The construction will begin on Gonsiori and Laikmaa streets, which will lead to the closure of Gonsiori street in the direction out of the city center between Laikmaa and Reimani streets and Laikmaa street between Gonsiori and Narva mnt towards Narva mnt.
18 linden trees on Ahtri and Kai streets and Narva Road will be replanted in a new location because of the construction of the Vanasadama tramway. Work on Kai Street will start today, on 11 April.
On Tuesday, 4 April, the second phase of the Vanasadam tram line construction work will begin and with that, Hobujaama Street and half of Laikmaa Street in the direction of Gonsiori Street will be closed. Narva mnt and the Hobujaama intersection will remain open. The construction work will cause changes to 27 bus line routes.
The construction of the Vanasadam tramway will cause traffic changes in the area around the intersection of Kursi Street and Põhja pst. until mid-September. From Tuesday 6 June, the section of Kursi Street in front of the Tallinn Creative Hub will be closed to traffic. From 26 June, the intersection of Põhja pst. and Kursi Street will also be closed.
From Monday, 3 July, the Narva mnt-Hobujaama-Laikmaa intersection will be closed as part of the next stage of the Vanasadam tramway construction. As such, tram lines 1, 2, 3 and 4 will be halted until the end of August. Viru terminal will be temporarily closed and public transport redirected.
Temporary tram line no. 6, which was created due to construction works on the Vanasadama tram line, will continue operating on the Tondi-Kopli route at least until the end of September, when tram traffic on all other lines has been restored. Tram lines no. 2 and 4 will restart operation at the beginning of September, with no. 1 and 3 doing so at the start of October. The city is considering the possibility of having line no. 6 operate on a permanent basis.